Occupational safety management

Material Topics: Process Safety Management; Corresponding Sustainability Principle: Safety and Harmony (GRI 2-25、3-3)

Management Approach and Elements
Importance to APC

"Process Safety Management," hereinafter referred to as PSM. Asia Polymer Corporation (APC) is classified as a Class C hazardous workplace; to prevent the occurrence of low-probability, high-hazard major accidents, strengthen the plant's internal PSM mechanism, coordinate with the Group's key implementation focus and external experts' requirements for continuous improvement, and constantly refine and implement Process Safety Management to meet external parties' expectations of Asia Polymer Corporation (APC).

Management Approach and Objectives

In accordance with the periodic implementation regulations for process safety assessments and the spirit of the Occupational Safety and Health Administration (OSHA), promote the PSM system and optimize management mechanisms to reduce the occurrence of high-hazard risk accidents, minimize company property losses, and safeguard worker safety.

Strategy
  • PSM Implementation Promotion: Commission the Group and external experts and scholars to provide technical consultation related to process safety within the plant, implement assistance from various units to drive project execution, understand work planning to forge consensus, and establish close partnerships.
  • Formulate Process Safety Performance Management: Track implementation progress based on the OSHA PSM system and the policies of the Group's Equipment Preventive Maintenance Environmental Risk Control Division (Environmental Protection Department), and establish a plant-wide annual Key Performance Indicators (KPI) management system to enhance work performance.
Management Impact
Positive/Negative Impacts
  • Actual Negative Impact - Failure to implement Process Safety Management
Negative Remediation and Preventive Measures

  • The Company has introduced the PSM system to prevent accidents through systematic management.
  • The Group's Equipment Preventive Maintenance Environmental Risk Control Division (Environmental Protection Department) annually conducts audits on the plant's PSM implementation progress.
  • Disclose chemical-related information within the plant on the information platform to ensure employees maintain basic knowledge of chemicals and response measures.
  • For Management of Change (MOC) cases, after preliminary hazard analysis, those with high risk levels will undergo Hazard and Operability Study (HAZOP) and Layer of Protection Analysis (LOPA) to ensure process safety.
  • For new processes or modification cases, execute a Pre-Startup Safety Review (PSSR) before startup, and conduct education and training for relevant personnel after completion.

Management Approach Targets and Performance
2025 Targets
  • Process Safety Incident Count (PSIC): 0
  • Process Safety Total Incident Rate (PSTIR): 0
  • Overall achievement rate of PSM KPI ≧ 90%
  • Annual average achievement rate of critical monthly PSM Management by Objectives (MBO) ≧ 95%
  • Establish an incident investigation platform, achievement rate ≧ 80%
2025 Performance
  • Process Safety Incident Count (PSIC): 0 (√)
  • Process Safety Total Incident Rate (PSTIR): 0 (√)
  • Overall achievement rate of PSM KPI:98% (√)
  • Annual average achievement rate of critical monthly PSM Management by Objectives (MBO): 102% (√)
  • Establish an incident investigation platform, achievement rate: 100% (√)
Short-term Targets(<3 years)
  • Process Safety Incident Count (PSIC): 0
  • Process Safety Total Incident Rate (PSTIR): 0
  • Overall achievement rate of PSM KPI ≧ 90%
  • Annual average achievement rate of critical monthly PSM Management by Objectives (MBO) ≧ 95%
Mid-to-Long-Term Targets(≧ 3 years)
  • Full participation in promoting PSM and continuously optimizing the process safety management system.
  • Introduce PSM Process Safety Management - Pre-Startup Safety Review (PSSR), and systematically manage various execution procedures and forms.
  • Cross-reference the PSM system with existing work within the plant and continue implementation.
  • Implement PSM compliance audits on a 3-year recurring cycle.
  • Coordinate with the Group's cross-plant audits for continuous optimization and improvement.
  • Reduce the occurrence of catastrophic leaks of highly hazardous chemicals to achieve the goal of zero process safety incidents.
Evaluation of Management Approach
Effectiveness Evaluation
  • Hold the PSM implementation and status meeting and coordination meeting each month.
  • Write monthly PSM execution reports and establish the execution status of commissioned research projects.
  • Formulate a performance system based on the checklist of information to be established for PSM introduction, which is tracked monthly by the Group's Equipment Preventive Maintenance Environmental Risk Control Division (Environmental Protection Department), to evaluate and review the monthly data establishment completion rate.
Grievance Mechanism
  • Report the PSM progress of the Linyuan Plant in the executive meeting, plant affairs meeting, and monthly coordination meeting.
  • Provide technical consultation related to process safety within the plant, coordinate projects executed by various units, maintain close contact with all units (including consulting parties), understand execution needs, and forge consensus.
Adjustment of Management Approach
  • Report the PSM progress of the Linyuan Plant in the executive meeting, plant affairs meeting, and monthly coordination meeting.
  • Continuously improve in accordance with external experts' requirements and regulatory amendments to align with the PSM execution direction expected by external parties.
  • Execute subsequent work according to the schedule and cross-reference with existing work within the plant to achieve work internalization and record accumulation.
Process Safety Management (PSM)
Major historical disasters (such as Bhopal, Kaohsiung, and Tianjin) demonstrate that process safety incidents involving hazardous chemicals pose far greater risks than individual safety events. Implementing Process Safety Management (PSM) is a global standard that helps companies effectively manage aging equipment, prevent low-probability, high-consequence (LPHC) catastrophic accidents, minimize unscheduled shutdowns, and reduce impacts on local communities.

Process safety incidents

To ensure operational safety, APC enforces standard operating procedures for initiators, conducts employee training, and continuously enhances its Process Safety Management (PSM) system. 2025, the Linyuan Plant recorded zero process safety incidents and zero transport safety incidents. (SASB RT-CH-540a.1、540a.2)
2025 Linyuan Plant Process and Transportation Safety Incident Statistics

(SASB RT-CH-540a.1、540a.2)

PSIC

0

PSTIR

0

PSISR

0

Transportation Safety Incidents

0

Note
1.
Process Safety Incident Count (PSIC)
2.
Process Safety Total Incident Rate (PSTIR) = (Total number of process safety incidents x [200,000 hours] / Total hours worked by all workers)
3.
Process Safety Incident Severity Rate (PSISR) = (Total score of process safety incident severity levels x [200,000 hours] / Total hours worked by all workers).
4.
0 process safety incidents occurred at the Linyuan Plant ; according to the Center for Chemical Process Safety (CCPS) process safety metrics, the severity level is Level 2, with a total score of 1 point.
5.
Total hours worked by all workers: Employees 506,811 hours + Non-employee workers (including contractors) 200,416 hours, totaling 707,227 hours.

Transportation safety management

The safety management of process operation, raw materials transportation, and product transportation are important to APC, and we have established safety management SOPs for related operations.

Raw Materials Transportation

To ensure transport safety, the APC Linyuan Plant primarily transports its main raw materials—ethylene and vinyl acetate—via underground pipelines, supplemented by tanker trucks. Pipeline safety is strictly managed through preventive maintenance, daily inspections, abnormality management, and emergency drills. All tanker trucks are certified, screened vehicles equipped with comprehensive emergency response plans and fully comply with relevant regulations. The transportation methods, quantities, and proportions of the main raw materials in 2025 are detailed in the table below:
Method of Materials Transportation and Proportion of the Linyuan Plant in 2025
Raw Material Transport Method Quantity (MT) Percentage (%)
Ethylene Underground pipeline 121,274 87.0
Vinyl Acetate Tanker 18,156 13.0
To ensure safety, APC products are transported via flatbed trucks, general trucks, and container trucks through qualified transport contractors under strict outsourced logistics regulations. Product transportation methods, quantities, and proportions for 2025 are detailed in the table below:
Methods of Product Transportation and Proportion of Linyuan Plant in 2025
Transport Method Quantity (MT) Percentage (%)
Trailers and trucks 33,668 25.0
Container trucks 101,002 75.0